// BASF Casestudy

STAR worked on the largest chemical production site in Belgium. Black Diamond was an EPC project that CB&I carried out at the BASF Antwerp site.
It was for the construction of a Butadiene factory in the period 2012-2014 and is estimated at a total cost of 200 to 250 million euros investment cost with about +50,000 man hours.
We have had about 10 people on the project at CB&I and then a few at subcontractors such as Hertel and Engie, in almost all construction disciplines, but especially:

  • Construction Management
  • Construction Supervision E&I / P&M
  • Contract management
  • QHSE
  • Commissioning
  • QA/QC
  • Document Control

// Vacatures

Vacatures in deze sector

Bekijk alle vacatures

Laat in twee klikken je CV achter

Bekijk alle vacatures
// Contact

Kom in contact

Laat je CV achter en we gaan op zoek naar het beste project dat bij je past. Goed genoeg is voor ons niet genoeg. Wij gaan tot het uiterste!

Full speed ahead · Full speed ahead ·

Kom in contact met onze Consultants

// Contact

Let's talk options

Full speed ahead · Full speed ahead ·

Kom in contact met onze Strategic Business Partner & Company Lawyer Sari

Dit veld is bedoeld voor validatiedoeleinden en moet niet worden gewijzigd.
// Meer opdrachtgevers

We hebben meer samenwerkingen voor je

STAR levert een toegevoegde waarde voor je bedrijf, door de pragmatische en adequate aanpak om kwalitatief hoogstaande mensen af ​​te leveren die aan onze wensen voldoen!